CLIENT PROJECT DESCRIPTION WORKS TERMINATED ON
Interporto Toscano "Amerigo Vespucci S.p.A." Execution of the general project viability and primary urbanization in the Interport Loc. Guasticce - Collesalvetti (LI) - Electrical systems
Under Works
Enel Produzione S.p.A. Turn Key Project.
Civil engineering works and extension of the Machines’ building for the improvement of the Lgoni Rossi geothermal plant
Under Works
Uno a Erre Italia S.p.A. Turn Key Project.
Execution of the new plant at. San Zeno – Arezzo.
Under Works
Frassino S.r.l. Execution of the technological installations for the conservative improvement of Villa La Banditaccia situated at Castagneto Carducci (LI).
2008
Parrocchia
S. Paolo della Croce
Turn Key Project.
Execution of a church with annexed spaces at Follonica.
Under Works
Comune di Radda in Chianti Turn Key Project.
Completion and finishing works of the restoration of Ex Palazzo Comunale.
2008
Enel Produzione S.p.A. Turn Key Project.
Restoration works of the geothermal museum “De Larderel” situated in piazza Leopolda at Larderello (PI).
2008
Project Costruzioni Scarl Execution of the technological installations at the parking block at Piazza Alberti in Florence.
2008
Orbetello Pesca Lagunare S.r.l. Turn Key Project – Execution of a prefabricated building for fish works – Località Topaie – Albinia (GR).
2006
Vetreria Operaia Lux S.p.A. Execution of the technological plants for the industrial development area in Loc. Pratelle at Montelupo Fiorentino (FI).
2005
Project Costruzioni Scarl Execution of the technological plants for the parking blocks of Piazza Caduti nei Lager in Florence.
2006
Unione Sportiva Virtus Turn Key Projectb.
Execution of the sporting centre Virtus Poggibonsi (SI).
2007
Terna S.p.A. Turn Key Project.
Execution of all civil engineering works for the HV substation of Ferrara.
2006
Parrocchia
SS. Pietro e Paolo
Turn Key Project.
Execution of a church and annexed spaces for cultural and catechesis events in Follonica (GR).
2007
Italiana Costruzioni 2000 Turn Key Project.
Restoration of the hotel complex HOTEL DEGLI ULIVI in SIENNA.
2006
Enel Produzione S.p.A. Lavori elettromeccanici ed elettrici presso la Centrale Idroelettrica di Bussolengo (VR).
2006
Project Costruzioni Scarl Execution of technological plants for the parking blocks of Piazza Beccaria in Florence.
2005
Saiagricola S.p.A. Turn Key Project.
Execution of the new wine celler stock at la Cantoniera of Monterufoli (PI).
2004
Santa Lucia S.p.A. Turn Key Project.
Execution of a tourist complex centre in San Gimignano (SI).
2005
Casa Vinicola Cecchi Turn Key Project.
Execution of a building composed of a
cellar and office spaces - Castellina in Chianti (SI).
2007
Enel Venezia Turn Key Project.
Execution of the primary distribution substation of Montecchio (VI).
2004
Irplast S.p.A. Execution of the technological installations in the new industrial development area of Loc.Terrafino - in Empoli (FI).
2005
Confcommercio Pistoia Turn Key Project.
Execution of the new headquarters of Apollo Complex - V.le Adua in Pistoia.
2005
Enel Lombardia Turn Key Project.
Execution of the primary distribution substation of Gorgonzola (MI).
2004
Eli Lilly Italia S.p.A. EXecution of various electrical works at the plant in Sesto Fiorentino.
2006-2008
Novartis Vaccines & Diagnostics S.r.l. Execution of various electrical and instrumentation works at the plant in Rosia.
2006-2008
Chiron S.r.l. Execution of various electrical and instrumentation works at the plant in Rosia.
2003-2006