| CLIENT | PROJECT DESCRIPTION | WORKS TERMINATED ON |
|---|---|---|
| Interporto Toscano "Amerigo Vespucci S.p.A." | Execution of the general project viability and primary urbanization in the Interport Loc. Guasticce - Collesalvetti (LI) - Electrical systems | Under Works |
| Enel Produzione S.p.A. | Turn Key Project. Civil engineering works and extension of the Machines’ building for the improvement of the Lgoni Rossi geothermal plant |
Under Works |
| Uno a Erre Italia S.p.A. | Turn Key Project. Execution of the new plant at. San Zeno – Arezzo. |
Under Works |
| Frassino S.r.l. | Execution of the technological installations for the conservative improvement of Villa La Banditaccia situated at Castagneto Carducci (LI). | 2008 |
| Parrocchia S. Paolo della Croce |
Turn Key Project. Execution of a church with annexed spaces at Follonica. |
Under Works |
| Comune di Radda in Chianti | Turn Key Project. Completion and finishing works of the restoration of Ex Palazzo Comunale. |
2008 |
| Enel Produzione S.p.A. | Turn Key Project. Restoration works of the geothermal museum “De Larderel” situated in piazza Leopolda at Larderello (PI). |
2008 |
| Project Costruzioni Scarl | Execution of the technological installations at the parking block at Piazza Alberti in Florence. | 2008 |
| Orbetello Pesca Lagunare S.r.l. | Turn Key Project – Execution of a prefabricated building for fish works – Località Topaie – Albinia (GR). | 2006 |
| Vetreria Operaia Lux S.p.A. | Execution of the technological plants for the industrial development area in Loc. Pratelle at Montelupo Fiorentino (FI). | 2005 |
| Project Costruzioni Scarl | Execution of the technological plants for the parking blocks of Piazza Caduti nei Lager in Florence. | 2006 |
| Unione Sportiva Virtus | Turn Key Projectb. Execution of the sporting centre Virtus Poggibonsi (SI). |
2007 |
| Terna S.p.A. | Turn Key Project. Execution of all civil engineering works for the HV substation of Ferrara. |
2006 |
| Parrocchia SS. Pietro e Paolo |
Turn Key Project. Execution of a church and annexed spaces for cultural and catechesis events in Follonica (GR). |
2007 |
| Italiana Costruzioni 2000 | Turn Key Project. Restoration of the hotel complex HOTEL DEGLI ULIVI in SIENNA. |
2006 |
| Enel Produzione S.p.A. | Lavori elettromeccanici ed elettrici presso la Centrale Idroelettrica di Bussolengo (VR). | 2006 |
| Project Costruzioni Scarl | Execution of technological plants for the parking blocks of Piazza Beccaria in Florence. | 2005 |
| Saiagricola S.p.A. | Turn Key Project. Execution of the new wine celler stock at la Cantoniera of Monterufoli (PI). |
2004 |
| Santa Lucia S.p.A. | Turn Key Project. Execution of a tourist complex centre in San Gimignano (SI). |
2005 |
| Casa Vinicola Cecchi | Turn Key Project. Execution of a building composed of a cellar and office spaces - Castellina in Chianti (SI). |
2007 |
| Enel Venezia | Turn Key Project. Execution of the primary distribution substation of Montecchio (VI). |
2004 |
| Irplast S.p.A. | Execution of the technological installations in the new industrial development area of Loc.Terrafino - in Empoli (FI). | 2005 |
| Confcommercio Pistoia | Turn Key Project. Execution of the new headquarters of Apollo Complex - V.le Adua in Pistoia. |
2005 |
| Enel Lombardia | Turn Key Project. Execution of the primary distribution substation of Gorgonzola (MI). |
2004 |
| Eli Lilly Italia S.p.A. | EXecution of various electrical works at the plant in Sesto Fiorentino. | 2006-2008 |
| Novartis Vaccines & Diagnostics S.r.l. | Execution of various electrical and instrumentation works at the plant in Rosia. | 2006-2008 |
| Chiron S.r.l. | Execution of various electrical and instrumentation works at the plant in Rosia. | 2003-2006 |